Integrating Tightening with PLC and MES

A tightening controller can work on its own, but on a production line it is usually part of a larger system. The PLC controls the station in real time: when the tool is enabled, with which program and what happens if the result is NG. The MES manages plant production: which part is being built, under which order and where the history of every tightening is stored. This page explains how the work is split and what data is exchanged.

What the PLC does

  • Detects that the part has arrived and is in position.
  • Enables the tool and tells it the right program or job.
  • Receives the OK or NG result and decides: release the part, request a retightening or send it to repair.
  • Coordinates tightening with the rest of the station: clamps, conveyors, robots or feeders.

The exchange uses digital inputs and outputs or an industrial fieldbus such as PROFINET, EtherNet/IP or Modbus TCP.

What the MES does

  • Knows which part, model or variant is being produced, and can tell the station which program to use.
  • Receives and stores the results of each tightening linked to the serial number or VIN.
  • Lets you look up a part's history later and generate quality reports.

The connection to the MES usually runs over the plant network, directly from the controller or through the PLC or an intermediate server. The level model between control and production management is described in the IEC 62264 (ISA-95) series.

What data is exchanged

  • To the controller: enable, program or job number, part identifier.
  • From the controller: OK/NG result, final torque and angle, program used, fastener count, tool status and alarms.
  • To the MES: the complete record of each tightening, and curves when the system stores them.

Which fields each controller provides is confirmed model by model. See result logging and traceability.

Common architectures

  1. Controller and PLC: the PLC runs the station and the controller stores results locally.
  2. Controller, PLC and MES: the PLC runs the station and the controller or the PLC sends results to the MES.
  3. Several controllers and a server: plant software collects results from many stations and passes them to the MES.

What to define before integrating

  • Who selects the program: the operator, the PLC or the MES.
  • How the part is identified and when the identifier is read.
  • What happens on a NG: retightening, lockout, repair station.
  • Which protocol and data format each link will use.
  • What happens if the network goes down: whether the controller stores results and sends them later.

Sources and references

  1. IEC 62264-1 — Enterprise-control system integration — Part 1: Models and terminology
  2. IEC 61131-3 — Programmable controllers — Part 3: Programming languages